There is good news and bad news.

Good news is the panels are now ready and could be delivered by 15th September.

Bad news is that a team to erect the building is not available until w/c 18th October. All other components for the building are ready for delivery. There may be a slot a little earlier to erect the building but is dependent upon confirmation from another of the company’s clients.